A design to strengthen external heat supply networks for checkpoint

Design carried out by our engineering organization on strengthening the external heat supply networks of the NTS. We have completed construction and design work.

A design to strengthen external heat supply networks for checkpoint

DESIGNING THE STRENGTHENING OF EXTERNAL NETWORKS

This working documentation considers the issue of measures to ensure the safety of engineering communications at the facility near the building of the automobile checkpoint.
The adopted technical solutions comply with the requirements of environmental, sanitary, fire-fighting and other standards in force in the territory of the Russian Federation, and ensure the operation of the facility that is safe for human life and health, while observing the measures provided for in the working drawings.
Working documentation developed on the basis of:
- technical specifications;
- approved project;
- current geological base
In the development of working documentation used regulatory documents operating in the territory of the Russian Federation.
1. This project provides for the installation of a monolithic channel on the noun. 2Du325h7 / 450PPU pipelines laid without channels on a monolithic reinforced concrete base. The channel device is necessary to ensure the normative distance from the projected building of the motor-mobile checkpoint according to SP 124.13330.2012.

PROJECT DOCUMENTATION OF THE STRENGTH OF NTS OUTSIDE HEAT SUPPLY NETWORK

2. The length of the monolithic channel is 18.0 m.
3. When organizing a construction site, work areas are separated on the ground by inventory safety fences.
Before starting work on the development of the soil, the heating system is to be opened by pits in order to clarify the depth of its position and location in the plan
Otshurfovku All communications within the trench.
Otshurfovke and opening of the heating network, under the supervision of representatives of organizations responsible for its operation.
Exclude sludge construction equipment and storage of building materials.
Development of the soil is provided in the metal mounts. Backfilling sand layered compaction.
4. All construction work must be carried out in strict accordance with SNiP 12-03-2001 "Labor Safety in Construction" and the project of production work (CPD), which is being developedстроительной организацией.