Heating point automation design for scientific research institutes

Our organization has completed the design and installation of an automation system for a heat point.

Heating point automation design for scientific research institutes

Working documentation for instrumentation and automation of a heat supply station

developed on the basis of the TK for the automation of ITP and the task of the "heat supply" group.

Provided for;

1. Control of the mixing pumps of the 2nd heating (1 pump working, one standby).

2. Control of the control valve KZ32 du32 using the PID-regulator meter TPM12-N.U.R company OWEN.

Installation of instruments and automation equipment to perform in accordance with SNiP 3.05.07-85

All metal parts and installations of control and automation must be grounded.

The symbols of the instrumentation and automation equipment are made according to GOST 21.404-85.

Pipeline conventions see kit.

Pressure gauges installed on horizontal pipelines are numbered 1-1, on vertical 1-2

The cable should be laid locally using cable structures specified in the specifications of this document.

Preparation of pipes and cables to produce after the control measurement of the length of the route.

Openly laid cables to fasten along the walls on horizontal sections with a pitch of 800mm. on vertical sections with 500mm pitch.

The equipment layout and cable routing should be clarified by location.

The equipment installed on the walls to mount on the profile K241U2.

Protective grounding (zeroing) to perform in accordance with the requirements of PUE.

 

Projects drawings PBX format pdf lay out on request …